Why is the launch of my energy community delayed?

Reasons why registration and launch can take longer – and what you can do about it.

If your registration or the launch of your community is taking longer than expected, it is usually down to one of the following:


​No suitable match yet: There is currently no suitable combination of generation and consumption on the same substation in your area. Setting up a community requires at least one suitable counterpart, that is, at least one generation and one consumption metering point (or a prosumer). Registration goes ahead as soon as suitable participants sign up.
​

No LEG in your municipality yet: Your municipality is not yet active and there is no active energy community in your area so far.
​

The grid operator's registration process is not possible or too restrictive: Some grid operators require elaborate procedures for registration – a qualified electronic signature (QES) via Swisscom, for example. Hurdles like these can delay the process or make registration impossible for the time being.
​

The grid operator is not ready yet: Some grid operators have not finished setting up their processes for LEG or for the data transfer. In that case the community can only go live once the grid operator is ready.
​

High one-off setup fees charged by the regional grid operator: A few grid operators still charge high one-off fees for setting up a community. Where these make it uneconomical, we may hold off on registering. Worth knowing: such fees may only be charged until the end of this year, so this obstacle will soon disappear.
​

A smart meter still to be installed: All participants need a smart meter. If one or more members do not have one yet, the metering operator has to install it first – they have three months to do so, free of charge. This can extend the lead time.
​

What you can do
​

Check the status of your registration and your community at app.upgrid.ch, where you will find the current position and the next steps. Share the invitation links from your dashboard with people in your municipality – the more suitable participants sign up, the sooner your community can start. And raise the subject of energy communities with your municipality; we are happy to support them in setting one up. For more specific tips, see «How can I speed up the launch of my energy community?».
​